Construction Safety and Health Plan: when you need one and who prepares it

A Safety and Health Plan sets out how health and safety will be managed on a construction project. It is required under the Safety, Health and Welfare at Work (Construction) Regulations 2013.

When is one needed?

When the project will last more than 30 working days or 500 person days, or involves a particular risk listed in the Regulations.

Who prepares it?

  1. Design stage: the PSDP (Project Supervisor Design Process) prepares the preliminary Safety and Health Plan. The client gives it to tenderers.
  2. Construction stage: the PSCS (Project Supervisor Construction Stage) develops it into the construction stage plan before work starts, and keeps it up to date.

What goes in it?

Project details, the people and roles involved, site rules, the particular risks and how they will be controlled, emergency arrangements, welfare, and how work will be coordinated between contractors.

The HSA’s free BeSMART.ie tool can help small contractors create a construction stage plan.