The Construction Regulations require certain records to be kept on site, or at the contractor’s office for works under 30 working days, and to be available to an HSA inspector.
Records to keep for every site
| Record | Kept by |
|---|---|
| Safety and Health Plan | PSCS |
| Notification to the HSA (where required) | PSCS |
| Site inductions given | Contractor / PSCS |
| Safe Pass and skills cards of everyone on site | Contractor, coordinated by PSCS |
| SPAs and risk assessments for each task | Contractor |
| Accident and dangerous occurrence reports | Contractor |
| Inspection and test records (scaffolds, excavations, lifting equipment) | Contractor |
| Safety File, handed over at the end | PSDP to client |
How My Work Folder helps
Certs, inductions, SPAs and site pack acknowledgements are kept together for each site, with dates and names, ready when someone asks.